If you’re planning a roof replacement, one of the first questions that comes to mind is how long the whole process will actually take. Nobody wants scaffolding on their property for weeks on end, and understanding the timeline helps you plan around work, family schedules, and the inevitable disruption.
The short answer? Most UK homes take between 2 to 7 days for reroof a house. But that’s quite a range, and several factors determine where your property falls on that timeline. Let’s break down everything you need to know about reroofing duration and what happens during the process.
What Determines Your Reroofing Timeline?
Not all reroofing projects are created equal. A small terraced house in South London will have a very different timeline compared to a large detached property in Surrey. Here are the main factors that influence how long your reroof will take.

Roof Size and Complexity
The bigger your roof, the longer it takes. That’s straightforward enough. But complexity matters just as much as size. A simple gable roof on a three-bed semi might only need three days, while a property with multiple roof planes, valleys, dormers, and chimneys could stretch to a full week or longer.
Properties in areas like Central London often have more architectural features that add time to the project. Victorian and Edwardian homes, common across South West London, typically have more complex roof structures than modern builds.
Your Choice of Roofing Material
Different materials require different installation methods and timescales:
- Concrete or clay tiles: Standard installation, usually 3-5 days for an average home
- Natural slate: Takes longer due to individual fixing requirements, add 1-2 extra days
- Flat roofing systems: Can be quicker for small areas but depend heavily on the membrane type used
The removal process also varies. Stripping old slate is more labour-intensive than removing concrete tiles, which affects the overall timeline.
Weather Conditions (The UK Wild Card)
Let’s be honest, British weather is unpredictable at best. Rain is the biggest enemy of roofing projects. Even light drizzle can halt work, especially during the vulnerable stages when the old roof is off but the new one isn’t fully installed.
Spring and summer generally offer better working conditions, but even July can bring surprise downpours. Roofers in London and Surrey typically build in buffer time for weather delays. A project quoted at four days might actually take six if rain intervenes.
Average Timelines for Different UK Property Types
Understanding how your specific property type affects the timeline helps set realistic expectations. Here’s what you can typically expect.
Small Properties (1-2 Bedrooms, Flats, Small Terraces)
- Timeline: 2-3 days
- Usually straightforward roof structures
- Less material to remove and install
- Quicker scaffolding setup
Medium Family Homes (3-4 Bedrooms)
- Timeline: 3-5 days
- This covers most semi-detached and detached homes across Surrey and South London
- May include one or two chimneys and some architectural features
- Weather buffer usually needed
Large Properties (5+ Bedrooms, Complex Designs)
- Timeline: 5-7+ days
- Multiple roof planes and features
- Significant material quantities
- May require larger crews or specialist work

Reroof A House Process: What Happens When
Understanding the day-by-day breakdown helps you know what to expect and when. Most projects follow a similar pattern, though the exact timeline varies based on the factors we’ve discussed.
Day 1: Setup and Demolition
The first day is often the noisiest. Scaffolding goes up (if not already erected the day before), and the old roofing material gets stripped away. Expect banging, scraping, and the sound of materials hitting the skip. Your home is at its most vulnerable during this phase, so roofers work quickly to get protective coverings in place.
Days 2-3: Preparation and Underlayment
Once the old roof is off, the team inspects the roof deck for any damage. Rotten battens get replaced, and structural issues are addressed. Then comes the breathable membrane or felt, followed by new battens. This creates the foundation for your new roof covering.
Days 4-5: New Roof Installation
The actual tile or slate installation happens now. Roofers work methodically across the roof, ensuring each piece is properly fixed. Ridge tiles go on last, along with any leadwork around chimneys and valleys. This is where the roof really starts to look finished.
Final Day: Guttering and Finishing
Here’s where City Guttering London often gets involved. The final day typically includes gutter work, and there’s a very good reason for that timing.
Why Reroofing Is the Perfect Time for Gutter Replacement
Many homeowners don’t realise that reroofing presents an ideal opportunity to sort out their guttering system. The scaffolding is already up, which eliminates the main cost barrier for gutter work.
Think about it practically. If your gutters are old or damaged, you’ll eventually need to hire someone, arrange scaffolding access, and pay for that separately. When the scaffolding is already there for the roof, you’re essentially getting free access to your guttering system.
Benefits of coordinating roof and gutter work:
- Scaffolding costs are already covered by the roofing project
- No need for a second round of disruption months later
- Your new roof is protected from day one by properly functioning gutters
- The whole roof-to-ground water management system gets renewed together
- Potential for better coordination between trades
City Guttering London regularly works alongside roofing contractors across South London, Surrey, and Hampshire. We can inspect your gutters before the reroof starts, provide a quote, and schedule the work to happen during those final days of the roofing project. It’s efficient, cost-effective, and ensures your entire water management system is in top condition.
What Can Slow Down Your Reroofing Project?
Even well-planned projects can face delays. Being aware of potential issues helps you stay prepared rather than frustrated.
Rain is the obvious one, but there are others. Material delivery problems occasionally crop up, especially for specialist tiles or slates. Conservation area properties in parts of London sometimes face permit delays. And occasionally, roofers discover hidden structural issues once the old roof comes off, which requires additional work before the new roof can go on.
Urban properties, particularly terraced houses in areas like South West London, can face access challenges. If there’s no side access and materials need to come through the house, that adds time. Parking restrictions can also slow down deliveries and waste removal.

Preparing for Minimal Disruption
A bit of preparation makes the whole process smoother. Clear your loft of valuable items, as dust and vibration are inevitable. Inform your neighbours about the timeline, especially regarding noise and possible scaffold overhang.
Move cars away from the work area, and ensure there’s clear access for material deliveries. If you’re working from home, consider whether the noise levels will allow that, particularly on the demolition day.
Before work starts, it’s worth having City Guttering London inspect your existing gutters. We offer free quotes within 45 minutes and can identify whether gutter replacement or repair would make sense during the reroof. With over 200 five-star reviews, our team knows exactly what to look for and can coordinate seamlessly with your chosen roofer.
Final Thoughts
Most UK reroofing projects take between 2 and 7 days, with the typical three-bed home landing somewhere in the 3 to 5-day range. Weather, material choice, roof complexity, and site access all play their part in the final timeline.
The key is choosing experienced professionals who can give you an accurate assessment based on your specific property. And don’t forget your gutters. While everyone focuses on the roof itself, your guttering system is what protects your walls and foundations from water damage.
If you’re planning a reroof in South London, Central London, Surrey, or Hampshire, get in touch with City Guttering London for a free gutter inspection. We’ll let you know whether your gutters can wait or whether coordinating the work with your roof replacement makes practical and financial sense. Our emergency repair service is also available if issues arise during the roofing work.